100 |
1 |
|
|a Bennett, F. Lawrence.
|9 43752
|
245 |
1 |
0 |
|a Critical path precedence networks :
|b a handbook on activity-on-node networking for the construction industry /
|c F. Lawrence Bennett.
|
260 |
|
|
|a New York :
|b Van Nostrand Reinhold,
|c 1977.
|
300 |
|
|
|a x, 98 p. :
|b diagrs. ;
|c 21 x 28 cm. +
|e 1 plantilla
|
336 |
|
|
|a texto
|2 rdacontent
|
337 |
|
|
|a sin mediación
|2 rdamedia
|
338 |
|
|
|a volumen
|2 rdacarrier
|
500 |
|
|
|a Plantilla para diagrama de flujo en bolsillo al final del item.
|
505 |
0 |
0 |
|a Contenido: Introduction -- Network development and basic calculations -- Calendar dating and "scheduling" -- Monitoring the network Schedule -- Another sample with some added frills -- Project costing with activity-on-node networks -- Computer processing of activity-on-node scheduling data.
|
650 |
|
7 |
|a INDUSTRIA DE LA CONSTRUCCION
|2 lemb2
|9 8393
|
650 |
|
7 |
|a INVESTIGACION OPERACIONAL
|2 lemb2
|9 165
|
650 |
|
7 |
|a ANALISIS DE RUTA CRITICA
|2 lemb2
|9 36331
|
650 |
|
7 |
|a CPM (ANALISIS DE REDES)
|2 lemb2